Distribution Centre – UK

King & Moffatt are currently in the final stages of commissioning the mechanical and electrical works to a printing pod extension at a Distribution Centre in the UK.

This multi-million-pound project was completed to a 10-week programme, to achieve this tight schedule the project team designed prefabricated pump skids which were manufactured offsite and then brought to site.

This project was a full design & build, including all chilled water, compressed air and general pipework, and was completed to BIM Level 2.